Method Statement: Torch-Applied Membrane Roof Waterproofing

Method statement PS-MS-01: PetroGrip APP/SBS torch-applied membranes on concrete roofs and podiums, covering priming, laps, upstands and flood test.

This method statement covers waterproofing of concrete roof slabs, terraces and podiums with PetroGrip APP or SBS torch-applied membranes, including single-ply and two-ply systems, upstands, outlets, penetrations, flood testing and protection.

It sets out hold points, acceptance criteria and the records to hand over, so consultants can approve it as a submittal alongside the PetroGrip datasheets.

Key specifications

Values shown are taken from the published brochure/TDS. Project acceptance follows the approved batch certificate and consultant specification.

Document
PS-MS-01, 4 pages
System
PetroGrip APP / SBS, single or two-ply, torch-applied
Side / end laps
Minimum 100 mm / 150 mm, end laps staggered by 300 mm
Upstands
At least 150 mm above finished roof level
Flood test
About 50 mm depth, at least 48 hours
Includes
Hot works safety, inspection and test plan, handover records

Applications

  • — Concrete roof slabs and terraces
  • — Podiums and trafficked decks under protection
  • — Industrial and commercial roofs

Related products

  • PetroGrip APP

    APP-modified torch membrane—2mm to 4mm with plain, aluminum, or granular surfacing.

  • PetroGrip SBS

    SBS-modified torch membrane—3mm and 4mm with plain, aluminum, or granular surfacing.