Method Statement: PETROUREA Polyurea Spray Application

Method statement PS-MS-05: PETROUREA hot-spray polyurea on concrete and steel, from surface preparation and priming to thickness and holiday tests.

This method statement covers surface preparation, priming, plural-component hot-spray application and quality control of PETROUREA pure polyurea coatings on concrete and steel, for roof and deck waterproofing, tanks and bunds, and industrial surfaces.

Grade, thickness and primer are selected per project for immersion, chemical, temperature, UV and mechanical exposure; chemical media and immersion limits must be confirmed for each project.

Key specifications

Values shown are taken from the published brochure/TDS. Project acceptance follows the approved batch certificate and consultant specification.

Document
PS-MS-05, 3 pages
System
PETROUREA 300–800 pure polyurea, plural-component hot spray
Hose temperature
Typically 70 – 85 °C
Mix ratio
1 : 1 by volume unless the grade data states otherwise
Surface preparation
Concrete shot-blast (ICRI CSP 3–5); steel blasted to ISO 8501-1 Sa 2½
Environment
Substrate at least 3 °C above dew point
Testing
Thickness grid, holiday test (immersion areas), pull-off adhesion

Applications

  • — Seamless roof and deck waterproofing
  • — Industrial tanks and bunds
  • — Steel structures under mechanical stress

Referenced standards

ISO 8501-1 · ICRI 310.2R · ASTM D4541 · ASTM D7234